Q2  2018 :   Land clearing and grading, utilities, curbing and temporary gravel of new rear parking area. Demolish existing rear parking and establish building pad.

Q3  2018 :   Foundation and structural frame construction of new auditorium
and youth room addition. 

Q4  2018 :   Wall framing, roofing, mechanical and electrical systems of new auditorium and youth room addition. 

Q1  2019 :   Exterior and interior finishes of new auditorium and middle/high school addition. Complete new rear parking.

Q2  2019 :   Completion/occupancy of new auditorium and youth room addition. Renovations of old auditorium and new Kid Focus spaces.

Q3  2019 :   Front parking revisions and improvements.

Q4  2019 :   Final Completion and Occupancy.